(영문) 대전지방법원 2015.03.18 2014가합105329

부당이득금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

Basic Facts

The plaintiff is an autonomous management body that consists of occupants to manage the 10-dong 1436 households located in Daejeon-dong-ro, Daejeon-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-dong-si

The Plaintiff, on April 5, 2013, intended to construct the existing central heating boiler system of the apartment of this case to convert the existing central heating system into each individual heating unit, publicly announced the limited competitive bidding (hereinafter “instant primary bidding”); and conducted the site site conference on April 15, 2013 with respect to the individual heating conversion works (hereinafter “instant construction works”).

At this time, the public announcement of the tender is limited by the provision that the participation in bidding is limited to a business that has no delay or experience in construction related to apartment construction.

As a result of the instant first bidding, the Plaintiff decided to conduct a bid, and decided to conduct a second bidding. On April 24, 2013, the Plaintiff issued a second bidding notice (hereinafter “instant second bidding notice”) with respect to the instant construction as follows.

Public notice of retender for individual heating conversion works;

4. Kind of bidding: Limited competitive bidding;

5. An enterprise which has no dispute, delay or abandonment with the council of occupants' representatives in connection with the 10 apartment construction works for participation in bidding;

7. One-time and place of document finishing: The apartment management office of a Si/Gun/Gu on April 26, 2013.

8. Date, time, and method 1) the site site consultation committee: April 26, 2013, and method 2) the apartment management office of a party: After the completion of documents, the examination of documents to be submitted, and individual notification to the eligible enterprise.

8. Date and method 1) Date and time: 10 April 30, 2013 (18: 2) Method of bidding: 11. Other matters, 61. The submission of the documents, and the submission of the site descriptions, to the companies which participated in the site descriptions, at the bidding of the apartment management office per apartment.