(영문) 서울동부지방법원 2021.01.28 2020가단134288

공사대금

Text

The defendant shall pay 16,400,000 won to the plaintiff and 12% per annum from September 14, 2020 to the day of complete payment.

Reasons

1. Around January 2020, the Plaintiff entered into a contract for construction works (hereinafter “instant contract”) with the Defendant on the terms and conditions that the Plaintiff would receive a contract for construction work (including value added tax) with respect to the construction work of the dyp design and installation work to be installed in the dyplate model (hereinafter “instant contract”). The Plaintiff’s completion of construction works from February 8, 2010 to February 20 of the same month from February 8, 2010, and completed the construction work from the Defendant during the period from January 21, 2020 to August 4, 2020, and the Plaintiff’s completion of construction works from the Defendant, including the entire number 10,00,000,000 won, and the total amount of KRW 40,000,000,000 from September 10, 202 to September 20, 200, or including the purport of the entire number 200,000 won.

Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 12% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from September 14, 2020 to the date of full payment, as the Plaintiff seeks, at least 57,200,000 won (=57,20,000 won - 40,800,000) and as sought by the Plaintiff.

2. It is so decided as per Disposition by admitting the plaintiff's claim on the ground that it is reasonable.