(영문) 서울남부지방법원 2014.05.02 2013가합106278

대여금

Text

1. The Defendants are jointly and severally liable to the Plaintiff for KRW 248,500,00 and Defendant B from March 28, 2014, and Defendant C.

Reasons

1. Indication of claim;

A. The Defendants agreed to borrow from the Plaintiff the sum of KRW 248,500,000 on July 30, 2009, KRW 30,000 on August 21, 2009, KRW 30,000 on August 21, 2009, KRW 8,500,000 on August 24, 2009, ④ KRW 20,000,000 on August 25, 2009, and ⑤ KRW 248,50,000 on August 28, 2009, and agreed to jointly and severally repay the said amount to the Plaintiff.

B. Therefore, the Defendants are jointly and severally liable to pay the Plaintiff damages for delay calculated at the rate of 20% per annum from March 28, 2014 to the day following the delivery of a copy of the instant complaint, and Defendant C is jointly and severally liable to pay the Plaintiff damages for delay calculated at the rate of 20% per annum from February 19, 2014 to the day of full payment.

2. Judgment by public notice (Article 208 (3) 3 of the Civil Procedure Act).