(영문) 서울고등법원 2020.02.06 2019나2002030

공사대금

Text

1. The judgment of the first instance, including the ancillary claim added by this court, shall be modified as follows:

Reasons

1. The reasoning for the court’s explanation concerning this part of the underlying facts is as follows, and it is identical to the part of “1. Basic Facts” from Nos. 11 to No. 85 of the reasoning of the judgment of the first instance, except for the partial dismissal as follows. Thus, this part is cited in accordance with the main sentence of Article 420 of the Civil Procedure Act.

An abbreviationd name established in the judgment of the first instance is also used below the same.

[Supplementary portions] From 1 to 14 under the upper part of the judgment of the court of first instance, the first to 6 under the upper part of the judgment of the court of first instance shall be raised as follows.

1) Plaintiff A, B, C, D Co., Ltd. and Defendant

2. As indicated in the amendment table to the instant Section 1, each of the instant Section 1 contracts entered into with each of the instant Section 1 contracts with an additional entry of the total construction period and total construction cost in each of the instant contract. The contract was amended several times due to delay in the conclusion of the contract, design modification, etc. due to the Defendant’s failure to conclude the

Finally, the construction period of the instant construction section 1 was extended from July 1, 2008 to October 31, 2012. The total construction cost was increased from KRW 151,975,00,000 to KRW 170,972,00,000.

2 Plaintiff E, F, G Co., Ltd. and Defendant

3. As indicated in the amendment table to the instant Section 2, each of the instant Section 2 contracts entered into with each of the instant Section 2 and stated the total construction period and total construction cost in each of the instant contract. The contract was amended several times due to delay in the conclusion of the contract, design modification, etc. due to the Defendant’s failure to set the budget.

Finally, the construction period of the instant construction section 2 was extended from July 1, 2008 to October 31, 2012. The total construction amount was increased to KRW 149,468,00,000 from the original KRW 136,93,50,000.

"Nos. 1 and 2" in Part 8 of the judgment of the first instance shall be "No. 12 and 13."