beta
(영문) 대구지방법원서부지원 2015.06.09 2013가단15962

손해배상(기)

Text

1. The Defendant (Counterclaim Plaintiff) pays KRW 10,401,207 to the Plaintiff (Counterclaim Defendant).

2. The plaintiff (Counterclaim defendant) shall be the opposing defendant.

Reasons

Basic Facts

On April 5, 2013, the Plaintiff newly built a shower room of the second floor on the land outside Daegu-gun, and a factory attached facilities that form the first floor parking lot on the land outside Daegu-gun, and awarded a contract to the Defendant for the construction of expanding the main gate (hereinafter “instant contract”). The content of the instant contract is as follows.

Article 1 [a summary of the Construction Work] 1: 2. The date scheduled for commencement of the Construction Work: B and 3 lots of land except for B: 1: the date scheduled for completion of the Construction Work: 30 days (excluding the amount of the Construction Work) from the date of commencement of the Construction Work: 57 million won; 3. The remainder of 51.3 million won (within 25 days after commencement of the Construction Work); 4, 570,000 won (payment within 10 days) and 3.5,000 won (payment within 10 days after completion of the Construction Work); 2.5,000 won (payment within 10 days after completion of the Construction Work); 3.5,00 won (payment within 10 days after completion of the Construction Work); and 3.5,000 won (payment within 10 days after completion of the Construction Work); and 2.5,000 won for delay to the Plaintiff; 2.3,016.

-.