beta
(영문) 대구지방법원서부지원 2015.10.08 2015가단11759

구상금

Text

1. Each Plaintiff:

A. As to KRW 77,163,760 and KRW 76,309,460 among Defendant A, Defendant A shall be from June 10, 2015 to August 17, 2015.

Reasons

1. Claim against the defendant A;

(a) Indication of claims: as shown in the Attached Form of Claim;

(b) Judgment made by the confession of applicable provisions of Acts (Article 208 (3) 2 and Article 150 (3) of the Civil Procedure Act);

2. There is no dispute between the parties as to the grounds for the attachment of the claim against Defendant B and the facts stated as the changed grounds for the claim.

Defendant B is jointly and severally liable with Defendant A to pay the amount of 11,700,000 won for indemnity and the amount of delay damages calculated at the rate of 20% per annum from August 21, 2015 to the date of full payment, which is the day following the service of the application for change of claim.

3. The plaintiff's claim against the defendants is justified.