건물명도등
1. The defendant delivers the real estate indicated in the separate sheet to the plaintiffs, and deliver the said real estate from May 1, 2015.
1. On June 5, 2014, the Plaintiff terminated the lease contract (a security deposit: KRW 10,000, KRW 650,000 per month, KRW 650,00 per month: the lease term: from June 11, 2014 to June 10, 2016) with the Defendant as to the real estate listed in the separate sheet on the grounds of the delay in rent by the Defendant indicating the claim, and accordingly, claims the delivery of the said building as a restoration, and also claims the return of overdue rent and unjust enrichment on the rent.
2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts (Judgment without holding any pleadings due to the submission of a written reply);