beta
(영문) 의정부지방법원 2016.09.07 2014가단11918

물품대금등

Text

1. The Defendants shall jointly and severally serve as KRW 21,602,00 on the Plaintiff and as a result, from August 29, 2013 to July 12, 2016.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment by public notice: Article 208 (3) 3 of the Civil Procedure Act.

3. Some of the rejection parts claim payment of damages for delay calculated at the rate of 20% per annum for the period from the day following the delivery date of a copy of the complaint in this case to the day of full payment. However, the portion exceeding the rate of 15% per annum among the above damages for delay claim pursuant to Article 2 (2) of the Addenda to the same provision (wholly amended by Presidential Decree No. 26553, Sep. 25, 2015) and Article 2 (2) of the Addenda to the same provision, is dismissed as there is no ground.