특정범죄가중처벌등에관한법률위반(뇌물)등
Defendant
A Imprisonment with prison labor of 10 years and fines of 460,000,000 won, and Defendant B shall be punished by imprisonment with prison labor of 1 year and 6 months.
Defendant .
Punishment of the crime
The Defendant, from April 21, 2009 to March 15, 2012, the Korea Water and Atomic Energy Co., Ltd. (amended by the Ministry of Strategy and Finance No. 2011, Jan. 24, 2011; hereinafter “Korea Water and Resources”) has overall control over the management of equipment to control various electronic signals (measurement variables) related to the operation of the said power plant while working as the head of the H in the First Power Center of the Mine Nuclear Headquarters of the Mine Energy Headquarters of the Republic of Korea, while working as the head of the H in the said plant.
1. On April 21, 201, the Defendant, from the representative director J, entered into a seal system supply contract equivalent to KRW 1.65 million with the contract amount ordered by the said H Team, and received KRW 100 million in cash from J in the case of the above contract and for convenience provision during the future supply. Accordingly, the Defendant, as a public official, received KRW 100 million in relation to the duties of the market-based public corporation’s officers and employees deemed public officials; 2. On March 25, 2011, the Defendant entered into a contract with the said H Team at a price of KRW 640,000,000,000 (hereinafter referred to as “L”), at a price of KRW 100,000,000,000,000,000,000,0000,000,000,000,000,000,000,000 won.
Therefore, around May 201, the Defendant received KRW 40 million in cash from the above M at the O restaurant in Yong-gun, Young-gun, Young-gun, and on September 2, 201, the Defendant completed the above delivery and service at the 2nd Y, Young-gun, Young-gun P.