채무부존재확인
1. Upon the primary claim against Defendant H added at the trial court, Defendant H was 90,744.
Basic Facts
The Plaintiff entered into a contract between the Plaintiff and Defendant H under contract with Defendant H for a temporary site, land, reinforced concrete, and machinery and equipment construction (hereinafter “instant basic construction”) during construction of a new building of 1,00 square meters in Sejong Special Self-Governing City I (hereinafter “instant building”), and agreed as follows:
(hereinafter referred to as “instant contract”). The construction period: The contract amount on April 2, 2012, and July 30, 2012, 2012, the date of commencement: (i) the timing and method of payment of the part of the base amount of KRW 183,000,000,000,000,000,000,000 until April 7, 2012; and (ii) the amount of KRW 30,000,000,000 at the completion of the floor of the first floor; and (iii) the amount of KRW 50,00,000,000,000,000,000,000 after the completion of the floor of the second floor; and
Additional processes are discussed later.
Defendant H received a total of KRW 180,000,000 from the Plaintiff to August 31, 2012 as the construction cost.
Of the construction of the instant building, Defendant B completed the construction work on the interior and exterior walls of the building; ② the construction work on the roof of the building; ② the construction work on the roof of the building; ③ the construction work on the ceiling of the building; ④ the construction work on the roof of the building; ④ the construction work on the stairs and floor stones; ⑤ the construction work on the roof of the building; ⑤ the construction of the stairs and floor stones; ⑤ the installation of a door door presses; and ⑤ the construction of each work performed by Defendant G et al. (hereinafter “the remainder of the instant construction”); and the construction work on September 11, 2012.
On September 11, 2012, the Plaintiff received KRW 180 million from Defendant H as the construction price for the instant building’s temporary installation, land, reinforced concrete, machinery and equipment, stone construction, stone construction, kitchen construction, roof and home passage construction, metal construction, tailing construction, glass construction, windows construction, painting construction, painting construction, and dumping construction,” from Defendant H on September 11, 201, below the receipt No. 4.