(영문) 서울서부지방법원 2020.12.24 2020고단2939

업무상과실공공용전기공급방해

Text

Defendant shall be punished by a fine of five million won.

If the defendant does not pay the above fine, KRW 100,000.

Reasons

Punishment of the crime

From September 2019, the Defendant performed the removal work of the third floor of the ground and the first floor of the underground floor located in Bupyeong-gu Incheon Metropolitan City, and on November 4, 2019, around 14:45, the Defendant ordered the construction of the retaining wall for the underground removal work to the construction site of the above construction site, and ordered the construction of the underground tent C to install the retaining wall for the underground removal work.

At this point, D road is an adjacent place, and there is a sign sign, which is a sign informing the Korea Electric Power Corporation that the Korea Electric Power Corporation is laid underground in the underground of the road. Therefore, there was a duty of care to check whether the underground facilities exist in the surrounding areas and prevent them from being damaged by gas, telecommunication, electricity, etc.

Nevertheless, the Defendant, despite being aware of the existence of a track for supplying electricity in the vicinity of the above site, failed to accurately verify the location of the track, and had an lecractorist with an occupational negligence ordering the construction work, and caused the Victim Korea Electric Power Corporation to perform a construction work for a scale of ground 0.4m high in depth and width, and caused the Victim Korea Electric Power Corporation to damage the underground transmission line and the underground transmission line between the eculatory section and the main section of the main section of the eculatory section to prevent electricity from being supplied to the Japanese 118,527 of Incheon City.

Accordingly, the Defendant interfered with the supply of electricity by destroying structures of public electricity due to such occupational negligence.

Summary of Evidence

1. Defendant's legal statement;

1. Part of the prosecution and protocol concerning the examination of suspects of the accused;

1. Statement of prosecutorial and police statements concerning E;

1. A written statement of the accusationF;

1. The report on completion of restoration, the progress map of the transmission line of the malfunction, the cadastral map and the section of the site of the malfunction, the results of cadastral survey, the response to approval of the occupation and use of a road, the permission of new construction, and the request for the perusal of the data on the approval of excavation, and the permission of the construction of a building;