(영문) 부산지방법원 2020.01.14 2019가단19708

대여금

Text

1. The defendant shall pay to the plaintiff the amount of KRW 124,377,497 and the amount of KRW 78,278,796 from August 9, 2019 to the date of full payment.

Reasons

1. According to the overall purport of Gap evidence No. 1 and No. 4 of the judgment as to the cause of the claim and the whole pleadings, among the facts as stated in the attached Form No. 1 and No. 4, the creditor shall be deemed to be "the plaintiff" and the debtor

Any fact recorded may be recognized and there is no evidence that obstructs it.

According to the above facts, the defendant is obligated to pay to the plaintiff 124,377,497 won in total including the principal and interest, etc. outstanding to the plaintiff and delay damages calculated at the rate of 12% per annum from August 9, 2019 to the date of full payment.

In response, the defendant asserted that the defendant's decision of bankruptcy and exemption against the representative director C cannot respond to the plaintiff's request, but the claim in this case is not a claim against the defendant's representative director C, but a claim against the defendant company which is a corporation.

2. Conclusion, the plaintiff's claim is justified.