(영문) 서울동부지방법원 2018.08.17 2017고정743

공익사업을위한토지등의취득및보상에관한법률위반

Text

Defendant

B, C, D, E, F, G, H, I, J, K, L, and M shall be punished by a fine of KRW 700,000.

Defendant

B, C, D, E, F, G, H, I, J, K, L.

Reasons

Punishment of the crime

Defendant

A, B, C, D, E, F, G, H, I, K, K, L, and M are the owners of the Songpa-gu Seoul Metropolitan Government P apartment units, and Q Housing Redevelopment and Development Project Association, the complainant, is the redevelopment partnership in progress for the above P apartment.

The owners of land, persons concerned, and other persons who do not include landowners or persons concerned, but have rights to the land to be expropriated or used or goods thereon shall deliver or transfer such land or goods to the project executor by no later than the commencement date of expropriation or use.

Nevertheless, Defendant A did not deliver the expropriated land to the victims Q&Housing Redevelopment Development and Improvement Project Association, the project implementer, by continuously occupying 503 of Songpa-gu Seoul apartment units P, which is the land to be expropriated until June 10, 2016, which was the date of commencement of expropriation of land.

Defendant

B until June 10, 2016, which was the date of commencement of expropriation of land, it did not transfer the expropriated land to the victim Qu Housing Redevelopment and Improvement Project Association, the project implementer, by continuously occupying 601 of Songpa-gu Seoul Metropolitan Government P apartment house 601.

Defendant

C until June 10, 2016, which was the date of commencement of expropriation of land, it did not transfer the expropriated land to the victim Qu Housing Redevelopment and Improvement Project Association, the project implementer, by continuously occupying 201 Songpa-gu Seoul Metropolitan Government P apartment house 201.

Defendant

D has not transferred the expropriated land to the victim Qu Housing Redevelopment Development Project Association, a project implementer, by continuously occupying Songpa-gu P Apartment 202, which is the land to be expropriated until June 10, 2016, which is the date of commencement of expropriation of land.

Defendant

E did not transfer the expropriated land to the victim Qu Housing Redevelopment Development and Improvement Project Association, the project implementer, by continuously occupying 303 of the Songpa-gu Seoul Metropolitan Government P apartment housing, which is the land to be expropriated until June 10, 2016, which is the date of commencement of expropriation of land.

Defendant

F The Seoul Special Metropolitan City, which is a land expropriated until June 10, 2016, the date of commencement of expropriation of land.