(영문) 서울중앙지방법원 2015.03.18 2015가합505729

공사대금

Text

1. The Defendant shall pay to the Plaintiff KRW 221,453,50 and the interest rate of KRW 20% per annum from January 1, 2015 to the day of complete payment.

Reasons

1. The Plaintiff’s determination of the cause of claim completed the construction work equivalent to KRW 310,898,50 (including value-added tax; hereinafter the same shall apply) in total due to the Plaintiff’s contract for interior works, such as interior works from around 2013 to the recent period, and the fact that the Defendant received KRW 89,445,00 from the Defendant does not conflict between the parties.

Therefore, the Defendant is obligated to pay to the Plaintiff the amount of KRW 221,453,50 (i.e., KRW 310,898,500 - KRW 89,445,00) and damages for delay calculated at the rate of 20% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from January 1, 2015 to the date of full payment, following the delivery of a copy of the application for the instant payment order, as requested by the Plaintiff.

2. In conclusion, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.