소유권이전등기
1. The Defendant (Counterclaim Plaintiff) indicated the attached Form 1, 2, and 1 of the land for a factory in Hannam-gun, Gyeongnam-gun, the Plaintiff (Counterclaim Defendant) on the land of 505 square meters.
A principal lawsuit and a counterclaim shall be deemed simultaneously.
1. Basic facts
A. The Plaintiff is the owner of a 3,639 square meters of land for a factory in Gyeong-gun, Gyeongnam-gun (hereinafter “1 land”), and the Defendant is the owner of a 505 square meters of land for a factory adjacent to the land in 1 (hereinafter “2 land”).
(b)The details of changes in ownership of land Nos. 1 and 2 are as follows:
(1) On October 6, 1987, E completed the registration of ownership transfer with respect to land No. 1 on April 22, 1987, and F, the representative director of the above company, constructed a steel-frame and steel-line contrut and slive roof two-story factories, restaurants, shower rooms, offices, boiler rooms (hereinafter “instant building”). The above company completed the registration of ownership transfer with respect to the instant building on November 24, 1987.
Then, Dong New Co., Ltd. completed the registration of ownership transfer in succession with regard to the land No. 1 and the building of this case on the grounds of successful bid by each auction on May 6, 2002.
(2) G completed the registration of ownership transfer on land No. 2 on October 29, 1962, and Defendant and H completed the registration of ownership transfer on July 11, 200 with respect to each share of No. 2 land on July 11, 200. The Defendant completed the registration of ownership transfer on April 6, 200 with respect to 1/2 shares of H on April 6, 2007 by completing the registration of ownership transfer on the ground of sale.
C. Of the instant building, the part (A) of the instant building connected each point of the items indicated in the separate sheet Nos. 1, 2, 3, and 1 is one square meter factory and the part (B) connected each point of the said map Nos. 4, 5, 6, 7, and 4 in sequence, among the parts of the instant building, the stairs of the Plaintiff’s office and the stairs of the said map No. 8, 9, 10, 11, 12, and 8 in sequence connected each point of the said map No. 8, 9, 10, 11, 12, and 8 square meters of water level (hereinafter “(A), (b), and (c), which are 3 square meters of water level in the part (c) connected each point of the said building (hereinafter “the part”) was constructed on the ground of the instant land No. 1 and the land No. 2 was over the boundary of the said land
In addition, on the ground of the second land, the indication of drawings 8, 22, 21, 21.