(영문) 인천지방법원 2019.02.19 2018가단218792

용역비

Text

1. The Defendant (Counterclaim Plaintiff) shall pay 150,000,000 won to the Plaintiff (Counterclaim Defendant) and its payment from April 21, 2018.

Reasons

1. Basic facts (the principal lawsuit and counterclaim shall be deemed to be filed together);

A. The Plaintiff is the representative director of Nonparty C Co., Ltd (hereinafter referred to as “C”) who conducts environment and plant-related technical service business, and the Defendant is a corporation that conducts shipbuilding business, technical service business, etc. as its intended business.

B. On January 30, 2018, D agencies under the Ministry of Land, Infrastructure and Transport publicly announced the implementation of plant research projects in 2018, where the total research period from April 2018 to December 2023, 202 with respect to the development of the E plant technology (hereinafter “instant task”) based on the National Land Transport Technology Promotion Act (hereinafter “instant task”).

C. On February 3, 2018, the Plaintiff entered into a consulting service agreement with the Defendant as follows (hereinafter “instant service agreement”) with respect to the instant task and received KRW 50,00,000 from the Defendant on February 6, 2018.

2. (1) Advice on how to develop, commercialize and implement technology related to the instant task; and (2) implementation of the Defendant’s request related thereto;

3. The remuneration and expenses (1) the remuneration for the advisory services shall be two hundred million won;

In this regard, the initial payment date and amount shall be limited to KRW 50,000,000 on February 5, 2018.

The remaining amount of KRW 150 million shall be completed on February 19, 2018.

The period of advisory services shall be until the date the task is selected, but if the defendant is not selected, the plaintiff shall return the full amount of remuneration received to the defendant.

(2) The Plaintiff shall make every effort to fully reflect the following Defendant’s conditions for the selection of the task in accordance with the scope and conditions of the contract set forth in paragraph (2) above.

(hereinafter collectively referred to as “instant service terms”). The Government contributions to F shall endeavor to ensure the present intended amount level, i.e., sufficient budget (presumed KRW 15 billion).

approximately KRW 2.5 billion out of the costs of manufacturing E plant shall be C or.