beta
(영문) 전주지방법원 2020.04.08 2019가단26009

물품공급대금등

Text

1. The Defendants are jointly and severally liable to the Plaintiff for KRW 20,190,00 and 5% per annum from December 22, 2018 to April 8, 2020.

Reasons

1. Indication of claims: It shall be as shown in attached Form (Grounds for Claims);

However, the Plaintiff claimed for the payment of damages for delay from December 21, 2018. However, even according to the Plaintiff’s assertion, the due date for which the Defendants agreed in their respective letters is until December 21, 2018, and the order for the payment of damages for delay from the following day shall be issued.

2. Applicable provisions of Acts: Judgment without holding each pleadings (Article 208 (3) 1 of the Civil Procedure Act and the main sentence of Article 257 (1) of the same Act);