(영문) 의정부지방법원 2015.08.27 2014가단52216

건물철거 및 토지인도 등

Text

1. The Defendant shall keep the following points in order: marks 14, 5, 4, 15, and 14 on the attached appraisal map among the land size of 876 square meters in Seocheon-si, Seocheon-si.

Reasons

1. In full view of the purport of the entire pleadings as to the grounds for the claim Nos. 1 and 2, the Plaintiff is the owner of the Cancheon-si C large-scale 876 square meters (hereinafter “instant land”). The fact that the Defendant, who was the owner of the D land adjacent to the instant land and was the owner of the D land 1,523 square meters and attached Table Nos. 14, 5, 4, 15, and 14 attached to the instant land, connects each point of (B) partial prefabricated-type building Nos. 25 square meters and the same appraisal of (B) partial prefabricated-type building Nos. 14, 5, 14, 15, and 14 on the ground of the instant land, can be acknowledged.

According to the above facts, the defendant is obligated to remove the above building to the plaintiff and deliver the part of the land possessed to the plaintiff 41.5 square meters.

2. If so, the plaintiff's claim of this case is justified and it is so decided as per Disposition.