(영문) 울산지방법원 2016.06.16 2016가합20035

물품대금

Text

1. The Defendant shall pay to the Plaintiff KRW 468,076,00 and the interest rate of KRW 15% per annum from December 22, 2015 to the date of full payment.

Reasons

1. Facts of recognition;

A. The Plaintiff is a company manufacturing engines and turbs, etc. inside and outside the 298-9 of the Hong-si, Chungcheongnam-si, and the Defendant is a company running the manufacturing business, etc. in Ulsan-gu, Ulsan-gu, 32.

B. On September 25, 2014, the Plaintiff: (a) supplied the Defendant with the “TALIMARJPPPPPERT” (hereinafter “instant goods”) KRW 96,776,000 (production from September 25, 2014; and from October 25, 2014 to February 9, 2015).

C. On February 9, 2015, the Plaintiff supplied goods to the Defendant, but the Defendant paid only KRW 528,700,000 out of the amount of goods.

[Ground of recognition] Unsatisfy, entry of Gap evidence 1 to 4, purport of whole pleadings

2. According to the above facts of determination, the Defendant is obligated to pay to the Plaintiff the remainder amount of KRW 468,076,00 (=the total amount of KRW 996,776,00 - the already paid KRW 528,70,00) and damages for delay calculated at the rate of 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from December 22, 2015 to the date of full payment, which is obviously a day after the original copy of the payment order was served.

3. In conclusion, the plaintiff's claim is justified, and it is so decided as per Disposition.