1. The Defendant shall pay to the Plaintiff KRW 206,426,471 as well as 20% per annum from December 24, 2014 to the date of full payment.

Reasons

1. H-BEM (298*201*9*9*14 on August 13, 2012) 400 tons from August 13, 2012 to August 12, 13, 2013 to 14, 320,00 on October 19, 2012, H-BEM (300*300*10*15) 103 tons on October 19, 201. 30 to 107. 8, 207, 30 to 30 to 10. 8, 207, 203 to 30 to 10. 8, 207, 207 to 30 to 15,207, 207 to 30 to 30 to 18. 18, 2013, 30 to 30 to 16. 16.27, 2016

A. The Plaintiff entered into each contract with the Defendant to lease steel products to the Defendant four times as follows, with the company supplying steel products (H-BAM) and steel products (H-BAM), and accordingly, delivered the steel products to the Defendant.

B. Of the rent under each of the above lease agreements, the Defendant repaid KRW 50,680,025 out of the total amount of KRW 257,106,496 from July 31, 2013 to December 31, 2013 to the Plaintiff by offsetting the amount payable and the amount of credit purchase. However, the Defendant did not repay the remainder of KRW 206,426,471 (=257,106,496 – KRW 50,680,025).

C. Therefore, the Defendant is obligated to pay the Plaintiff the unpaid rent of KRW 206,426,471 and the damages for delay calculated at the rate of 20% per annum from December 24, 2014 to the date of full payment after the delivery of the copy of the instant complaint.

2. Article 208 (3) 3 of the Civil Procedure Act applicable to Acts and subordinate statutes;