사기등
A defendant shall be punished by imprisonment for one year.
However, the execution of the above punishment shall be suspended for two years from the date this judgment becomes final and conclusive.
Punishment of the crime
The defendant is a person who is engaged in construction business by lending a construction license of D Co., Ltd. from the 5th floor of Busan Dong-gu Seoul Metropolitan Government to work as a managing director.
1. Forgery of private documents;
A. On February 10, 2012, the Defendant: (a) had no right to the right to operate the restaurant at the construction site of the construction site of the construction site of the 4 Section G in Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, by using a computer to pretend that he/she had the right to operate the restaurant; (b) to pretend that he/she had the right to operate the restaurant: “Standard subcontract for Construction Works (basic, alteration)”: Land and sand transportation and blasting, construction site: The contract amount: nine billion won; (c) the supply amount; (d) nine billion won; (d) the prime contractor’s address; (e) the name, name, I/F; and (d) the address of the subcontractor at Chungcheongnam-gu, Chungcheongnam-do; and (e) the name, J, K: name, and name of the construction project at the construction site; and (e) signed a standard subcontract for the construction project subsequent to the name of the said F.D. corporation.
Accordingly, for the purpose of uttering, the Defendant forged a copy of the subcontract in the name of F, a private document on rights and obligations.
B. On April 15, 2012, the Defendant: (a) prepared a standard subcontract agreement for construction works (basic, modified) in the same manner as in the foregoing office; (b) upstream and transport of construction works; (c) the construction site: Gwon in Chungcheongnam-gun, Chungcheongnam-do; and (d) the construction period: April 15 through 20, 2012; (b) the principal contractor’s address: E (ju), name I/F; and (c) the subcontractor’s address: (d) the name and address adjacent to the said F’s name.
Accordingly, for the purpose of uttering, the Defendant forged a copy of the subcontract in the name of F, a private document on rights and obligations.
2. On February 2, 2012, the Defendant is forged at the office of (M)M located in the Dong-gu Busan, Busan, for the purpose of uttering of the relevant investigation document.