(영문) 서울동부지방법원 2019.01.30 2017가단134806

보증채무금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

As the cause of the instant claim, the Plaintiff, on March 22, 2010, lent KRW 100 million to C after one month of the due date, and the Defendant guaranteed the above loan obligations. Therefore, the Defendant asserts that the Defendant is liable to pay KRW 100 million and the damages for delay thereof to the Plaintiff.

It is not sufficient to recognize that the Plaintiff guaranteed the above loan obligations only with the statement of evidence Nos. 1 and 1-1, and there is no other evidence to prove otherwise.

The plaintiff's assertion is without merit.

The plaintiff's claim is dismissed.