beta
(영문) 의정부지방법원고양지원 2017.09.07 2017가단74456

손해배상(기)

Text

1. The defendant shall pay 83,00,000 won to the plaintiff and 15% per annum from April 8, 2017 to the day of complete payment.

Reasons

Comprehensively taking account of the purport of each statement in Gap evidence Nos. 1 through 4 (including the number of branch numbers), the plaintiff loaned a total of KRW 140 million to the defendant three times from March 19, 2014 to May 12, 2014; the plaintiff in the case where the plaintiff filed a criminal complaint against the defendant for fraud (No. 2015 type No. 29946) between the plaintiff and the defendant on September 18, 2015, "the defendant shall be paid KRW 120 million to the plaintiff; the defendant shall be paid KRW 300,000,000 per month from October 20 to December 20, 2016 until December 30, 2016; the defendant lost the above profit of KRW 500,000,000,000,000,000 per month during which the payment was made within the period of delay (No. 200,000,07).

Therefore, the defendant is obligated to pay damages for delay at the rate of 15% per annum from April 8, 2017 to the day of full payment, which is the day following the delivery of a copy of the complaint of this case sought by the plaintiff to the plaintiff, since the defendant is obligated to pay damages for delay at the rate of 83 million won per annum under the Act on Special Cases concerning Expedition, etc. of Legal Proceedings.