1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

6. If a successful bidder fails to conclude a contract within 30 days from the date he/she is notified of the determination of the successful tender, along with evidential documents (such as written consent from residents) to secure the successful tender, the bid bond shall revert to the window of the creative city and shall be publicly notified;

7. He/she shall determine the successful tender lane for a person who has tendered with the highest price among persons who have tendered at least the lowest bidding price as a unit price tendering (the estimated sale quantity) and effective tendering with a minimum bidding price;

8. A successful tenderer whose bid or winning prizes are void shall be prepared and submitted within 30 days from the date of receipt of the notice of the decision on the successful bid and at the time of entering into a contract with the document evidencing his/her intention to secure the winning by release (such as written consent from residents), and if the document required is not submitted, the winning will become void and the bid bond will vest in the window of the

If there is any false or other unlawful fact in the submitted documents, the winning shall be invalidated, and the bid bond shall vest in the window of the original city. A.

On October 4, 2013, the head of Changwon-si, the Defendant-si, the head of Changwon-si, the head of Changwon-si, the Changwon-si, a public announcement of a competitive bid (hereinafter referred to as the “instant public announcement”) held on October 15, 2013, with the minimum bid price of KRW 6,942/m2, and the opening date of the bid (hereinafter referred to as the “instant bid”) to sell dredging land of KRW 909,074 square meters (hereinafter referred to as the “instant dredging land”). The public announcement related to the instant case is as follows.

B. On October 15, 2013, the Plaintiff and Samju Co., Ltd. (hereinafter “Triju”) participated in the instant bidding. As a result of opening the bidding on October 15, 2013, the Plaintiff selected as a successful bidder the highest bidder who tendered 11,610 won/land size as a successful bidder (hereinafter “instant successful bidder”). The Plaintiff, who participated in the bid on KRW 7,19/land size, was not designated as a successful bidder.

C. On October 16, 2013, the head of Changwon-si, the head of the Changwon-si notified the instant award decision to the third party, and on November 14, 2013, the third party and the instant case.