beta
(영문) 서울서부지방법원 2020.02.13 2019가단14861

약정금

Text

1. The Defendant’s KRW 80,000,000 as well as 5% per annum from May 31, 2010 to December 12, 2019 to the Plaintiff.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Article 208 (3) 1 and Article 257 of the Civil Procedure Act.

3. According to the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings (amended by Presidential Decree No. 29768, May 21, 2019), the statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings is 12% per annum from June 1, 2019. Thus, the part of the claim for damages for delay seeking payment in excess of the annual 12% from June 1, 2019 is rejected.