공사대금 등
1. The Defendant’s KRW 1,017,60,000 and KRW 447,369,392 among the Plaintiff, respectively, shall be KRW 570,230,608.
1. The description of the grounds for the claim shall be as specified in the attached Form;
2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);
3. The plaintiff shall claim for the payment of damages for delay calculated at the rate of 20% per annum from the day after the day of this judgment to the day of complete payment.
However, the provision on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553, Sept. 25, 2015) that reduces the statutory interest rate from 20% per annum to 15% per annum under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553, Sept. 25, 2015) was amended and promulgated as of Sept. 25, 2015, and came into force from October 1, 2015, the delay damages from the date following the date of this judgment to the date of full payment shall be recognized only within 1