beta
(영문) 대구지방법원 2015.04.23 2014고단6641

폭력행위등처벌에관한법률위반(공동주거침입)등

Text

Defendant

A Imprisonment for eight months, Defendant B shall be punished by a fine of five hundred thousand won, and Defendant C shall be punished by a fine of one million won.

Reasons

Punishment of the crime

【Status of the Defendant】 Defendant A is the Eno-K Port F, Defendant B is the Democratic Labor Relations Headquarters G, Defendant C is the Democratic Labor Relations Headquarters G, and Defendant C is the Democratic Labor Relations Headquarters H.

On January 7, 2009, the Korea Electric Power Corporation started construction of transmission line lines in order to supply the power transferred to the transformation station located in the Sungsan-gun from the Gyeongnam nuclear power plant to the Daegu Power Station and the Elderly Power Station, and completed construction (basic, assembly, and inter-line construction) with the exception of J located in the Cheongbuk-gun from among the 40-term transmission towers.

On the other hand, Cheongdo residents and external organizations, such as the Cheongdo Residents and the Daegu Environmental Campaign Association, interfered with the construction of the J transmission tower located in I, and the Corporation was suspended from July 3, 2012. On March 7, 2013, 222 organizations, such as Green Party and Daegu Environmental Campaign Association, jointly and severally formed "K", and on April 26, 2013, residents of the 21st group constituted "the Countermeasures against the I Transmission tower" and continued to hold a public and private assembly or demonstration.

On October 8, 2013, the Republic of Korea filed an application with the Daegu District Court for the injunction against obstruction of construction against the opposite residents and the outside power 23 persons, and the said provisional disposition was accepted on February 13, 2014, the construction resumed from July 21, 2014.

1. The Defendants’ Joint Democratic Nowon-gu Headquarters of the Republic of Korea and the Democratic Nowon-do Headquarters planned to organize “L” to hold an assembly at the construction site of a transmission tower under the pretext of supporting the residents of I during the demonstration in the construction of the transmission tower, and then held an assembly with the Cheongdo residents and the members of “K” among the Cheongdo residents, who participated in more than 200 members, such as the Democratic Nowon-gu et al. in the construction site of the transmission tower located in Cheongdo-gun, Cheongdo-gun, from August 27, 2014 to 20:00.

Defendants jointly with P, Q, R, S, T, and Democratic Labor Relations Steering Board on the same day, and hold a meeting before the entrance entrance of the construction site at around 19:10 on the same day, and the Cheong-do residents, “to directly see the transmission tower,” and leave the entrance.