약정금
1. The Defendant shall pay to the Plaintiff KRW 125 million with the interest rate of KRW 15% per annum from August 4, 2016 to the day of complete payment.
1. On January 5, 2015, non-party C (the representative director of the plaintiff) decided to purchase the above 7,785.16 square meters of land E and the above 2,86.78 square meters of land (around 1,586.78 square meters) from Kimhae-si, the defendant representing the defendant on 2015, and agreed to purchase the down payment and intermediate payment at KRW 50,000,000,000. The defendant ( de facto, the above D) did not construct and complete the above 105 factory up to April 30, 2015, and C did not pay the remainder at the time of completion of the contract (the C was completed, and the purchase price was 2,950,000,000,000,000 won and 2,000,000,000 won and 15,000,000 won and 2,015,00,000).
2. Judgment on the plaintiff's request, etc.
A. The Plaintiff’s judgment on the Plaintiff’s claim is the cause of the instant claim, and the cancellation of the said sales contract.