(영문) 창원지방법원 2020.10.29 2019가합531

공사대금

Text

1. The Defendant’s KRW 236,586,850 for the Plaintiff and KRW 5% per annum from October 4, 2019 to October 29, 2020, and the following.

Reasons

(b) construction after the settlement of accounts,* business details* - removed, packing, concrete construction - integrated installation of earth, installation of ground-to-soil, installation of ground-to-water, installation of ground-to-land, installation of 3,000 metres in unit size, 3,690,000 metres in 1,151 metres in 110,000 metres in 26,654,000 BOX 1.51.52 850,000 metres in 4,204,200 Ma 1.51.52,51.53 EA 12,000 Ma636,000 metres in 1,230 metres in 1,230 metres and 1,654,000 metres in east

D. On November 9, 2017, the Plaintiff and the Defendant drafted “C Contract for Additional Parts of Civil Works” (hereinafter “instant Additional Contract”) and the content thereof are as follows.

All equipment units related to the Saturdays shall be settled in accordance with the work log.

1) Poke usage fees *10POK Tran *100,000 per month: Settlement shall be made in accordance with the work log. *06W,000,000 per month; settlement shall be made in accordance with the work log as of the work log formed at the time of injection *06W, 03POK . 2) exump removal *25ton 80,000 per month and settlement shall be made in accordance with the work log.

2. In principle, the work on a structure other than a contract shall be conducted separately;

*L-type retaining wall* OL-type retaining wall* All the above-mentioned works on other structures are constructed with the consent of the owner and shall be settled in accordance with the work series after the completion of the monthly work.

The surtax is a separate amount.

E. On February 13, 2018, the Plaintiff prepared a “written confirmation of work for additional works of civil engineering works” (hereinafter “instant work confirmation”) and obtained the Defendant’s confirmation, and the details thereof are as follows.

1) From December 1, 2017 to January 31, 2018, 2018: Wron (36,000,000 won) *0.6Wron (600,000 won): On December 6, 2017: Wron work (600,000 won): Wron work (600,000 won) on December 6, 2017: Wron work (600,00 won) on November 29, 2017: Wron work (60,000 won) on November 29, 2017: August 83, 2018: 826 Wron removal total: 826:0,000 +60,000,000 won, 000 won = 30,000 won, 080,000 won-10,000 won-106m of retaining wall) *60,605m