(영문) 대구지방법원서부지원 2016.11.16 2015가단14154

대여금

Text

1. The Defendants jointly and severally pay to the Plaintiff KRW 116,281,679 and KRW 109,674,238 among them.

Reasons

1. According to the purport of Gap evidence No. 1 and evidence No. 10, the plaintiff loaned KRW 147,30,000 to defendant A on June 24, 2013, the interest rate of KRW 9.8% per annum, the loan period of KRW 69, and the delay compensation rate of KRW 25% per annum. The defendant Eul guaranteed the defendant A's obligation under the above loan contract. The plaintiff notified the plaintiff of the early cancellation of the above loan contract on May 4, 2015 due to delay in repayment of principal and interest, and as of August 3, 2015, the debt as of August 3, 2015 remains 109,439,138, the principal and interest amount of the loan of KRW 235,100, 607,441 won per annum.

Therefore, the Defendants are jointly and severally liable to pay to the Plaintiff damages for delay calculated at the rate of 25% per annum from August 4, 2015 to the date of full payment with respect to KRW 116,281,679 and KRW 109,674,238 among them.

2. In conclusion, the plaintiff's claim of this case is justified, and it is so decided as per Disposition.