(영문) 전주지방법원군산지원 2015.02.05 2014가합1746

공사금

Text

1. As to the Plaintiff KRW 161,50,000 and its KRW 11,300,00 among them, the Defendant shall start on March 25, 2014, and the remainder of KRW 150,200.

Reasons

1. The Defendant with the indication of the claim: (a) entrusted the Plaintiff with the steel frame construction of a new A factory in March 10, 2014 to KRW 124,30,000; (b) even though the Plaintiff completed on March 24, 2014, the Plaintiff did not pay KRW 11,30,000 out of the said payment; (c) the Plaintiff was entrusted with the steel frame construction of a new MTV plant in the Hanyang system Co., Ltd. in March 24, 2014 to KRW 400,400,000; and (d) even after the Plaintiff completed the construction on June 3, 2014, the Plaintiff did not pay KRW 150,200,000 out of the said payment and damages for delay from the date following the completion date of each construction.

2. Judgment based on the recommendation of confession, Article 208 (3) 2 of the Civil Procedure Act and the main sentence of Article 150 (3) of the same Act.