beta
(영문) 의정부지방법원 2015.07.03 2015가단15009

물품대금

Text

1. The Defendant shall pay to the Plaintiff KRW 27,662,030 as well as 20% per annum from March 25, 2015 to the date of the full payment.

Reasons

Comprehensively taking account of the overall purport of the pleadings Nos. 1 and 2, the Plaintiff may recognize the fact that the Plaintiff supplied ready-mixeds equivalent to KRW 27,662,030 after concluding a contract for supply of ready-mixeds with the Defendant on October 13, 2014.

Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay at the rate of 20% per annum from March 25, 2015 to the day following the delivery of the original copy of the instant payment order, which is the next day from March 25, 2015.

Therefore, the claim of this case is reasonable, and it is so decided as per Disposition.