beta
(영문) 서울남부지방법원 2016.06.08 2016가단13554

공사대금

Text

The Defendant’s KRW 66,00,000 and KRW 46,000 among the Plaintiff’s KRW 5% per annum from December 17, 2014 to March 4, 2016.

Reasons

Facts of recognition

On May 7, 2012, the Plaintiff completed the construction by receiving a subcontract from the Defendant for the construction of a new apartment building for the new building of the new building for the new building of the new building for the new building for the new building of the new building for the new building, the Defendant agreed to pay the Plaintiff the remainder of the construction cost of KRW 45,000,000 from October 31, 2014 to December 31, 2014, including the costs of lawsuit and the penalty, and the Plaintiff paid KRW 20,000,000,00 including the costs of lawsuit and the penalty, but the fact that the Defendant thereafter paid KRW 40,00,000 to the Plaintiff may be recognized by the purport of the entire pleadings and arguments.

Judgment

Therefore, the defendant is liable to pay to the plaintiff damages for delay of 66,00,000 won (86,000,000 won - 40,000,000 won) and 46,000,000 won, which is the day following the last payment date stipulated in the above agreement, to December 17, 2014, which is the day following the last payment date stipulated in the above agreement, to March 4, 2016, 5% per annum stipulated in the Civil Act, and 15% per annum stipulated in the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from the next day to the day of complete payment; 20,000,000 won from March 5, 2016 (20,000,000 won from the day following the delivery date of the complaint of this case to the day of full payment).

Therefore, the plaintiff's claim of this case is justified within the scope of the above recognition, and it is so decided as per Disposition.