beta
(영문) 대구지방법원포항지원 2015.11.10 2015가단8467

공사대금

Text

1. The Defendant’s KRW 80,000,000 as well as 20% per annum from August 26, 2015 to September 30, 2015 to the Plaintiff.

Reasons

In light of the overall purport of the arguments in Gap evidence Nos. 1 and 2, on January 29, 2015, the plaintiff was awarded with a contract for retaining wall construction from the defendant on March 13, 2015, among the multi-family house construction in the Nam-gu, Chungcheongnam-gu, Chungcheongnam-do, Chungcheongnam-do, 240 in the south-do, Chungcheongnam-do, Chungcheongnam-do, the Namnam-do, and completed the retaining wall construction on March 13, 2015. The plaintiff and the defendant set the cost of retaining wall construction as KRW 80,000,000 and

Therefore, the defendant is obligated to pay to the plaintiff 80 million won for the above contract construction work and to pay damages for delay calculated at the rate of 20% per annum from August 26, 2015 to September 30, 2015 and 15% per annum from the next day to the day of full payment, as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, which is the day following the delivery of a copy of the complaint of this case sought by the plaintiff as a result of the due date.

[The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (wholly amended by Presidential Decree No. 26553, Sep. 25, 2015; effective Oct. 1, 2015) and Article 2(2) of the Addenda, the statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from October 1, 2015 is 15 per annum. Thus, the Plaintiff’s claim is accepted within the above recognition scope, and the remainder is dismissed as it has no reason.