beta
(영문) 서울중앙지방법원 2015.09.25 2014가단5222124

양수금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

The Plaintiff, after having concluded a monetary loan agreement with the Industrial Bank of Korea on June 23, 2006 and received the loan, lost the benefit of time due to the delayed payment of the principal and interest. As of March 14, 2014, the amount of the above loan amount as of March 14, 2014 is KRW 569,957,790 in total (i.e., the loan principal amount of KRW 309,214,787 in interest of KRW 260,743,04 in interest of KRW 30,70 in interest of KRW 260,70 in interest of KRW 787 in interest of the loan principal). The above loan claim was finally transferred to the Future Savings Bank, Inc., a limited liability company specializing in asset-backed securitization, a combined asset management company, a U&S-A limited company, and X-AB-AB-B-A-A-A-B

However, the evidence submitted by the plaintiff alone is insufficient to recognize the existence of the above loan claim, and there is no other evidence to acknowledge it. Therefore, the plaintiff's assertion is without merit

Thus, the plaintiff's claim of this case is dismissed for reasons.