공사대금
1. The Defendant’s KRW 31,80,000 as well as 6% per annum from October 11, 2018 to July 2, 2019 to the Plaintiff.
1. Comprehensively taking account of the overall purport of the pleadings as to the statements in Gap evidence Nos. 1 through 3 and Eul evidence Nos. 1 and 2, the defendant awarded a new construction order for the Daejeon Seosung-gu D warehouse/rein building (hereinafter "the building of this case") on February 28, 2018 and subcontracted the construction of reinforced concrete (hereinafter "the building of this case") to the plaintiff from February 20, 2018 to April 20, 2018. The plaintiff started the construction of this case at that time and completed the construction of the above warehouse/reinduit building ordered by the defendant, and the plaintiff was approved for use on June 5, 2018 from February 20, 2018 to April 20, 2018.
4. Until June 18, 178,200,000 won in total were paid six times as the construction price in this case, and the defendant may, at the plaintiff's request, recognize the fact that the plaintiff paid 10,000,000 won directly to E.
2. Determination
A. According to the above facts, the Defendant is obligated to pay to the Plaintiff the remainder of KRW 31,800,000,000 (=220,000,000 - 178,200,000 - 10,000,000) out of the construction price of the instant case and delay damages therefrom.
Meanwhile, the Plaintiff asserts that the Defendant should pay the labor cost of KRW 3,600,000 as well as KRW 1,434,300, which the Plaintiff invested by the time of completion of the instant building. However, it is insufficient to recognize that the Defendant had the labor cost or the cost of goods to be settled separately from the instant construction contract, and there is no other evidence to acknowledge this differently.
B. The Defendant asserted that the Defendant spent 147,785,600 won on behalf of the Plaintiff, including compensation for delay caused by the Plaintiff’s delay in construction work, in addition to the above construction cost of KRW 188,200,000 paid directly to the Plaintiff or directly to the subcontractor, and paid by substitute payment of KRW 1,004,00 to the Plaintiff.