(영문) 의정부지방법원 고양지원 2018.10.12 2017가단94849

공사대금

Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 15,500,000 to the Plaintiff (Counterclaim Defendant) and its related amount from June 1, 2017 to October 12, 2018.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Fact-finding;

A. On March 22, 2017, the Plaintiff entered into a contract with the Defendant and the Gangnam-gu Seoul Metropolitan Government for the construction of the design (hereinafter “instant restaurant”) of the instant restaurant (hereinafter “instant restaurant”) (hereinafter “instant construction”) with the following terms, in the course of operating the interior construction contractor in the name of “C”.

(1) Period: Construction period: (2) Construction cost as of March 24, 2017 and as of April 30, 2017: 1.5 million won (excluding value-added tax 10.5 million won): < Amended by Presidential Decree No. 11717, Mar. 23, 2017; Presidential Decree No. 27947, Mar. 23, 2017; Presidential Decree No. 27907, Apr. 14, 2017; Presidential Decree No. 28139, Apr. 2, 2017; Presidential Decree No. 28179, Apr. 38, 2017; Presidential Decree No. 28170, May 2, 2017; Presidential Decree No. 2815, May 2, 2017>

함. 계약서는 사전에 제출한 견적내역에 준하며 공사진행 중 견적내역 외의 변경사항 발생 시 상호 협의 후 진행 여부를 결정함 ⑤ 공사의 협조사항 : ㉠ 설비공사 시 피고는 원고에게 적극 협조함, ㉡ 기물과 간판 사인 및 의자ㆍ탁자에 관해서는 원고의 의견을 참고하여 피고가 발주함, ㉢ 전기공사 시 증설공사와 이로 인한 배전함공사는 피고가 책임짐, ㉣ 냉난방 시설은 피고가 시설해야 하며 원고는 냉난방에 이상이 없도록 감리ㆍ감독함, ㉤ 피고가 준비할 소품에 관해서는 원고와 협조하여 시행함

B. After that, G, the husband of the Plaintiff, carried out the instant construction, and conducted the joint-use construction business with the trade name called “H”, I was awarded a subcontract for the part of the joint-use construction by G and connected Aluminium flusium flusium (hereinafter “Alumin”) to the upper part of the cooking body of the instant restaurant kitchen on May 9, 2018.