(영문) 대구지방법원경주지원 2015.07.21 2015가단1393

공사대금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. The Plaintiff’s assertion is obligated to pay the Plaintiff the remainder of the construction cost of KRW 24,250,000, excluding the remainder of the construction cost of KRW 28,250,000, excluding the remainder of the construction cost paid to the Plaintiff, as the Plaintiff was awarded a contract for construction cost of KRW 52,250,00 among the extension works of the Multi-Purpose D High School located in Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, Chungcheongnam-gun, Seoul, by the Field Director C on behalf of the Defendant, from May 2014 to January 2015.

2. It is not sufficient to acknowledge that the Plaintiff completed the construction work equivalent to KRW 52,250,000 on account of the contract for the said construction work from the Defendant solely with the descriptions of the evidence Nos. 3, 4, and 5, and there is no other evidence to prove otherwise.

Therefore, the plaintiff's above assertion is not accepted.

3. In conclusion, the plaintiff's claim is dismissed as it is without merit. It is so decided as per Disposition.