beta
(영문) 울산지방법원 2020.10.15 2020가합11434

채무불이행에 따른 손해배상청구

Text

1. The Defendant: (a) 288,460,00 won to Plaintiff A; (b) 165,460,000 won to Plaintiff B; (c) 17,930,000 won to Plaintiff C; and (d) 136.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Grounds for recognition: Judgment by public notice (Articles 208 (3) 3 and 257 (1) of the Civil Procedure Act);

3. Some rejection parts of the Plaintiffs A, B, C, D, and E seek payment of damages for delay from January 1, 2019, Plaintiff F from May 1, 2018, Plaintiff G from July 1, 2018, and from July 1, 2018 to June 11, 2020, each of the instant complaint was served on the Defendant by each of the instant complaint. However, since the liability for damages due to nonperformance is an obligation with no fixed due date, the Plaintiffs’ respective claims for damages for delay exceeding the scope recognized in the disposition are rejected.