beta
(영문) 대전지방법원 2015.05.14 2014가단41770

공사대금

Text

1. The Defendant shall pay to the Plaintiff KRW 26,420,00 and the interest rate of KRW 20% per annum from September 30, 2014 to the day of complete payment.

Reasons

1. In full view of the facts that there is no dispute between the parties to the judgment as to the cause of the claim, and the purport of the entire pleadings in the statement in Gap evidence Nos. 1 through 3, the plaintiff entered into a contract for construction works with the defendant on August 2, 2013 as of August 2, 2013; the date of commencement; August 2, 2013; the date of completion; and November 10, 2013; thereafter, the plaintiff and the defendant adjusted the construction cost to KRW 31,420,00; the plaintiff completed the construction works on November 10, 2013; and the plaintiff was recognized to have received KRW 5,00,000 from the defendant on March 3, 2014.

According to the above facts, the Defendant is obligated to pay the Plaintiff the remaining construction cost of KRW 26,420,00 (=31,420,000 - 5,000,000) and damages for delay at the rate of 20% per annum from September 30, 2014 to the date of full payment, which is the day following the delivery date of the original copy of the instant payment order sought by the Plaintiff after the payment deadline for the above construction cost.

2. The defendant's defense against the plaintiff's defense is insufficient to acknowledge that the plaintiff's defense was defective in the part executed by the plaintiff's repair work until the repair work is completed, since there are defects such as the water leakage of the floor due to the incidentalism of the main water pipe in the 1st underground floor in Ireland, and the water leakage of the main water pipe in the 1st underground floor in the 1st underground floor, and the 8,467,200 won in the PVC floor in the 1st underground floor in the 1st underground floor in the 2,467,200 won in the 8,467,200 won in the 2,3 evidence (including the base number) in the 2, and

3. It is so decided as per Disposition by the assent of all participating Justices on the ground that the plaintiff's claim is reasonable.