(영문) 서울중앙지방법원 2018.08.09 2018가단28707

대여금 청구의 소

Text

1. The Defendant’s KRW 50,000,000 as well as annual 30% from October 8, 2007 to July 13, 2014 to the Plaintiff.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. A judgment without holding any pleadings (Articles 208(3)1 and 257(1) of the Civil Procedure Act) (Article 208(3)1 and Article 257(1) of the same Act) [Plaintiffs claim interest or delay damages at the rate of 36% per annum from October 8, 2007 to the date of full payment. However, the part which exceeds the interest rate set forth in the Interest Limitation Act is null and void as the contractual interest. Thus, the Plaintiff’s claim for 30% per annum, the maximum interest rate set forth in the Interest Limitation Act, which was enforced within the scope of the agreed interest rate from October 8, 2007 to July 13, 2014; 25% per annum, the maximum interest rate set forth in the Interest Limitation Act, which was enforced within the scope of the agreed interest rate from the next day to February 7, 2018; and 24% per annum from the next day to the date of full payment];