(영문) 광주지방법원 2019.10.23 2019가단504021

공사대금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

The plaintiff asserted from the defendant that the defendant completed remodeling construction works for Class II neighborhood living facilities of the Gwangju Mine-gu, Gwangju District in the amount of KRW 75,402,807, and the defendant did not pay the price and caused the claim in this case. Accordingly, the defendant sold the above building to D on May 27, 2018. D entered into a remodeling construction contract with D on the above building, and the plaintiff accepted the above construction works from E, and the plaintiff did not dispute that the defendant did not contract the above construction works to the plaintiff, so it is insufficient to recognize it only by the statement of subparagraphs 1 and 3 as to the fact that the plaintiff received the above construction works from the defendant, and there is no other evidence to prove it otherwise.

Therefore, the plaintiff's claim of this case is dismissed as it is without merit, and it is so decided as per Disposition.