(영문) 광주지방법원해남지원 2016.01.26 2014가단4115

공사대금

Text

1. The Defendant: (a) KRW 19,00,000 for the Plaintiff and 5% per annum from February 27, 2015 to January 26, 2016.

Reasons

1. Basic facts: Article 4 (Prohibited Payment Terms and Conditions for Construction) from September 3, 2013 to December 15, 2013, Article 3 (Work Price) of Article 2 (Work Price) of B Housing Construction Work (Work Price) 114,00,000,000 won (Work Price) located under Article 1 (Name C): Part payment of KRW 40,000 (Work Price at the time of commencement of Construction Work): Article 8 (Construction Change) (Work after Completion of First-Slobbb), Article 2 (Work Price)

1. Even during the execution of this project, the Plaintiff may change the portion of the specifications if deemed necessary. In the event that the extension of the construction period and the increase or decrease of the construction amount are necessary, the Plaintiff and the Defendant shall consult and decide on the matters to be insignificant shall be borne by the

2. The modification of any specifications caused by the plaintiff on the part of the plaintiff during the construction shall enter into force after obtaining prior written approval from the supervisor of the plaintiff.

Terms and conditions of the attachment are 1st floor 30 square rooms, living rooms, toilets (hereinafter omitted) around the 5th floor of steel reinforced concrete

A. On September 2, 2013, the Defendant awarded a contract to the Plaintiff on September 2, 2013 for the construction of a single-story concrete slab housing (hereinafter “instant building”) on the ground (hereinafter “instant construction”).

(hereinafter “instant contract”). The main contents of the instant contract are as follows.

B. The Plaintiff completed construction under the instant contract, and the Defendant obtained approval for the use of the instant building on January 20, 2014.

C. The completed building area is 120.9 square meters.

[Ground of recognition] Facts without dispute, Gap evidence Nos. 1 and 2, the purport of the whole pleadings

2. Determination on the claim for additional construction costs

A. The Plaintiff and the Defendant agreed to construct a building with the area of 30 square meters in the instant contract, and the construction cost was set at KRW 114,00,000 (=3,800,000) as of the 30 square meters.

After concluding the instant contract, the Defendant demanded that the Plaintiff construct the instant building by increasing the size thereof, and the Plaintiff and the Defendant.