(영문) 대전지방법원 2014.02.20 2013가합103890

체비지대장상 소유자명의변경절차 이행 등

Text

1. All of the plaintiffs' primary claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Facts of recognition;

A. According to the Urban Development Act, the Defendant is the party to the instant project, which is the official, low-class four district urban development project in Seo-gu, Seo-gu, Daejeon (hereinafter “instant project”).

(2) The Busan Savings Bank extended loans of KRW 4,113,00,000 on December 31, 2010 and KRW 103,201,896 on November 25, 2002 to the Taean General Construction Corporation, and the Busan District Bank extended loans of KRW 6,53,00,000 to the Taean General Construction on July 7, 2009.

However, on August 16, 2012, Busan Savings Bank was declared bankrupt by each Busan District Court on March 7, 2012 and the plaintiffs were appointed as bankruptcy trustee on March 7, 2012.

Until the date of closing argument in this case, the comprehensive construction in Taean is insolvent.

B. On May 2, 2004, the defendant entered into a comprehensive contract for the project of this case on May 2, 2004, and the main contents of this case are as follows. 8) The payment method for the progress payment: The payment method for the progress payment shall be converted to the land allotted by the authorities in recompense for development outlay, and the payment in kind shall be made in kind (general provisions) 1. The defendant entered into an urban development project of the area of the area of the urban development project of the urban development project of the area of the urban development project of the area of the urban development project of the area of the urban development project of the area of the Taeananan, which is to be implemented under the Urban Development Act, and the comprehensive construction of the Taeananananananan

(2) Contracts that need to be additionally prepared in accordance with a construction contract between the defendant and the Taean General Construction Contract or any other administrative procedure by separate regulations stipulated in the relevant Acts from the authorization (approval) to the completion of a project shall be entirely subject to all the conditions of this contract.