(영문) 인천지방법원 2015.07.10 2014가합4220

공사대금

Text

1. Defendant M shall be KRW 15,200,00 for Plaintiff B, KRW 11,139,500 for Plaintiff G, and KRW 3,000,00 for Plaintiff I, and each of them.

Reasons

1. Determination as to the claims against Defendant J, K, and L by Plaintiffs A, D, E, F, and C

A. On September 2012, Plaintiff A’s assertion of the parties, Plaintiff A, D, E, F, and C concluded a contract between Defendant N and Defendant N for the construction of a new multi-household house on the ground of Seo-gu Incheon, Seo-gu, Incheon, with the construction cost of KRW 24,690,00 for tin and interior works, and completed the construction in accordance with the said contract. Defendant J failed to receive the construction cost of KRW 14,690,000 from Defendant J.

Plaintiff

D around July 2012, between Defendant J’s agent and Defendant N, the contract was concluded between tin and 20,000,000 won for electrical construction among the new construction works for multi-household houses on the ground of Seo-gu Incheon, Seo-gu, Incheon, and the construction work was completed in accordance with the said contract. However, Defendant J did not receive the said construction cost of KRW 20,00,000.

Plaintiff

E Around August 2012, Defendant J’s agent entered into a contract with Defendant N on KRW 24,144,800 with respect to the construction cost of the Consolidated Construction among the new construction works of multi-household housing in Seo-gu Incheon, Seo-gu, Incheon, and completed the construction work in accordance with the said contract. However, Defendant J did not receive the said construction cost of KRW 24,14,800.

Plaintiff

Around November 2012, F entered into a contract with Defendant J’s agent on KRW 14,900,000 with respect to the construction of a newly built multi-household house on the ground of Seo-gu Incheon, Seo-gu, Incheon, with the construction cost of KRW 14,90,00. The construction was completed in accordance with the said contract. However, Defendant J did not receive the construction cost of KRW 11,40,000 from Defendant J.

Plaintiff

C around July 2012, between Defendant N and Defendant N’s agent, the contract was concluded between Defendant N with respect to reinforced concrete construction work among the new construction works of multi-household houses on the Seo-gu Incheon P ground, Seo-gu, Incheon, with the construction cost of KRW 38,067,30. The construction work was completed in accordance with the said contract, and the construction cost of KRW 10,167,300 was not paid from Defendant K.

Plaintiff

E is Defendant K around August 2012.