손해배상(기)
1. Of the judgment of the court of first instance, the part against the plaintiff corresponding to the subsequent order of payment shall be revoked.
1. The Defendant’s liability for damages was contracted by the council of occupants’ representatives of Daejeon-gu Daejeon-gu on October 30, 2014 for construction period from November 3, 2014 to 120 days, and the Defendant removed the front 3,5Ra of the entrance and exit of the said apartment for the said construction work; the Plaintiff was at the front gate of the entrance and exit of the said apartment on December 5, 2014, in which the sidewalk block was removed and the soil was revealed due to the said accident; the Plaintiff suffered injury, such as the mouths, urines, etc. requiring treatment for about six weeks; from December 5, 2014 to December 8, 2014 to December 3, 2014, and there was no dispute between the parties to the instant construction work and the number of 1 to 3,000, including the number 1 to 4,000, and the number 1 to 3,000.
In light of the following circumstances revealed by each of the above evidence, i.e., the part on which the sidewalk block was removed includes the front part of the entrance stairs and slope, and there was a risk of accidents due to the misunderstanding or breaking away of soil caused by the soil exposed to pedestrians who get out of the stairs, and ii) the Defendant did not take all measures such as placing a sign or installing a passage so that pedestrians can safely pass on the part of the construction work, it shall be deemed that the above accident occurred due to the Defendant’s negligence in failing to take safety measures at the time of performing the construction work for replacing the sidewalk block, and thus, the Defendant is liable to compensate the Plaintiff for damages caused to the Plaintiff.
2. Scope of liability for damages
A. According to each of the evidence Nos. 4 and 4, the Plaintiff’s active damages 1 medical treatment costs and medicine expenses included in the evidence Nos. 4 and 4. From December 5, 2014 to January 29, 2016.