(영문) 수원지방법원성남지원 2015.11.25 2015가합2429

대여금

Text

1. As to KRW 210,00,000 and KRW 70,000 among them, the Defendant shall pay to the Plaintiff the year from June 3, 2015 to September 30, 2015.

Reasons

1. On October 17, 2002, the Plaintiff borrowed KRW 70 million to the Defendant on December 31, 2004 due date for repayment. Since then, on November 18, 2005, the Plaintiff received a judgment in favor of all the following: (a) the Plaintiff filed a lawsuit against the Defendant on November 18, 2005 (this Court Decision 2005Da15139); and (b) the Defendant paid the Plaintiff KRW 70 million and the amount equivalent to 20% per annum from June 3, 2005 to the date of full payment.

Therefore, the plaintiff shall be paid the amount of money from the defendant under the above judgment, but since the plaintiff is still unable to receive it, the lawsuit of this case has been filed for the extension of prescription. The defendant is obligated to pay to the plaintiff the above 70 million won, damages for delay 140 million won per annum from June 3, 2005 to June 2, 2015, and damages for delay 70 million won as to the above 70 million won from June 3, 2015 to the day of full payment.

2. Article 208 (3) 3 of the Civil Procedure Act: