용역대금 등
1. The Defendant’s KRW 35,720,00 and the Plaintiff’s annual rate of KRW 6% from January 18, 2018 to February 13, 2019, and the following.
1. Facts of recognition;
3. A design outline 1) Site area: 10,203 square meters (Around 3,086.4 square meters): A 10,203 square meters (around 2: 3,086.4 square meters): A 4th floor on the ground: A summary of the design area of the 5th floor (4th floor): A factory and office welfare (office, restaurant, dormitory, gold-type warehouse), one floor (5: 1,772 square meters (536.0 square meters): A 1,739 square meters (a 526.1 square meters) (a 526.1 square meters), and a 1,409 square meters (a 42.2 square meters) (a 426.2 square meters) (a 1,195 square meters (a total of 36.7 square meters) (a 1,617 square meters).
4. Design and supervision expenses 1) Design expenses: 1,850 x 50,000 x 92,500 x 2) Management expenses: Expenses for permanent supervision of construction supervision of general law firm x 6,000,000 x 8 months x 3) Total amount of design supervision expenses: 92,500,000 x 48,000 x 400,000 = 140,500,000 x 4) UNCOMT: design expenses (-) 500,000 x 5) additional tax (AT separate from VT);
5. In total amount of design expenses: 33% of the design cost for the first part payment (11% of the design cost) in the first part payment (34% of the design cost) in the first part payment (34% of the design cost at the time of receipt of the construction permit: 30,000 won in the first part payment (34% of the design cost) in the first part payment (34% of the design cost) in the first part payment (30,360,000 in the first part payment): 3,000 won in the first part payment (34% of the design cost) in the first part payment at the time of receipt of the construction permit: 31,280,000 won in the first part payment (31,280,000), 100,000 won in the first part payment (34% of the design cost): 1,000,000 won in the second part payment (10,000 won in the design cost) in the second part payment (4) in the design cost).
7.(1) The preparation of the statement of calculation of the construction cost and the statement shall, in principle, be of the additional actual cost settlement. 6) The additional statement of the cost of design and supervision increased or decreased due to the increase or decrease in the area to be undertaken after the contract is executed in accordance with the 1,850 square table, shall continue to run after consultation on the revision in accordance with the terms and conditions of this contract, on the basis of KRW 50,00
On August 28, 2015, the Defendant: (a) between the Plaintiff and the Plaintiff on August 28, 2015, “this case’s building”).