양수금 등
1. Defendant A Co., Ltd. and B jointly and severally with the Plaintiff KRW 65,753,720, and KRW 50,130,297, as to the Plaintiff’s KRW 65,753,720.
1. Basic facts
A. The Korean Bank Co., Ltd. (hereinafter “Nonindicted Bank”) extended a loan to Defendant A Co., Ltd. (hereinafter “Defendant Company”), and on October 25, 2007, KRW 100 million on October 30, 2008 (which shall be extended to October 25, 2013) and KRW 19% per annum (in arrears for at least three months) and extended a loan on September 27, 201 by setting the credit term of KRW 20 million on September 27, 2012, and Defendant B jointly and severally guaranteed each of the above obligations against Nonparty Bank of the Defendant Company.
B. On December 24, 2014, Defendant Company and Defendant B lost the benefit of time due to the delayed payment of each of the above obligations against Nonparty Bank, and Nonparty Bank transferred each of the above loans to Defendant Company and Defendant B (hereinafter “instant loans”) to the Plaintiff, and notified Defendant Company on January 16, 2015, and Defendant B on the 20th day of the same month, respectively.
C. By January 15, 2016, the principal and interest of the instant loan claims are KRW 65,753,720 in total, and the principal and interest are KRW 50,130,297 in total.
On January 15, 2013, Defendant B donated real estate listed in the separate sheet (hereinafter “instant donation”) to Defendant C, and completed the ownership transfer registration (hereinafter “instant transfer registration”) under Article 919 of the Daejeon District Court’s red support receipt on the 16th day of the same month.
E. At the time of donation of this case, Defendant B did not have any property other than the real property listed in the separate sheet.
[Reasons for Recognition] Defendant Company: Each entry in the evidence No. 1 to No. 4, and the purport of the whole pleading
2. Assertion and determination
A. According to the facts found in the determination as to the claim against Defendant Company and Defendant B, the Defendant Company and Defendant B jointly and severally liable to pay to the Plaintiff the amount of KRW 65,753,720 of the principal and interest of the instant loan and KRW 50,130,297 of the principal and interest of the instant loan and delay damages calculated at the rate of 19% per annum from January 16, 2016 to the date of full payment.
B. Determination as to the claim against Defendant C