구상금
1. Defendant A and Defendant B jointly and severally filed against the Plaintiff KRW 279,625,405 and KRW 278,183,072 among them, from October 27, 2014.
1. Basic facts
A. According to the credit guarantee agreement and joint and several sureties contract concluded on June 17, 2008 on June 13, 2013, 2013, the date of the conclusion of the credit guarantee agreement and the joint and several sureties contract, the guarantee number EF guarantee term on June 16, 2009 (the change to June 12, 2015 thereafter) on June 12, 2014 (the change to June 12, 2015) the guaranteed amount of KRW 100 million on June 12, 2014 (the change to June 12, 2015 thereafter) the guaranteed amount of KRW 180,000,000 and KRW 200,000,000,000 and KRW 200,000,000,000 and KRW 200,000,000 and KRW 20,000,000 were immediately paid to the Plaintiff’s guaranteed debt and its guaranteed obligation.
Meanwhile, the rate of damages for delay determined by the Plaintiff is 12% per annum from December 1, 2012 to the present.
B. (1) Defendant A submitted to the Industrial Bank of Korea a credit guarantee certificate issued by the Plaintiff pursuant to the credit guarantee agreement of this case, and obtained a loan of KRW 100,00,000 from the Industrial Bank of Korea on June 17, 2008. In addition, Defendant A submitted a credit guarantee certificate issued by the Plaintiff pursuant to the credit guarantee agreement of this case to the Industrial Bank of Korea on June 13, 2013, and obtained a loan of KRW 200,000 from the Industrial Bank of Korea on October 1, 2014, Defendant A forfeited the benefit due to the credit guarantee accident of this case on October 27, 2014, Defendant A subrogated the Industrial Bank of Korea on a total of KRW 281,731,112 (= agreement related to KRW 100,643,715, KRW 2781,397,97).
3) The Plaintiff spent KRW 1,441,167 by subrogation in order to preserve the claim related to each credit guarantee agreement of the instant case, and KRW 1,166 incurred a final delay damages. 4) Meanwhile, on October 27, 2014, the Plaintiff received reimbursement of KRW 3,548,040 from the Defendant A.